May 15, 2001 N.P. Carleton Installation of Granite Track for Short Delay Line ================================================== The re-installation of the granite track took place, 1-7 April, in steps listed below. I list them in detail, in case the next operation is done by persons unconnected with the present one. 1.) We took the cover off the shipping crate while it was still on the truck in order to see which end was which, since it was critical to start into the building in the correct orientation. 2.) We cleared the path that the thing must follow in the building. It needs all the space at the SE end of the main room in order to swing around under the corner of the optical table and travel down the SW side of the room. After negotiating the step down, it must go straight on, putting its end under the main vacuum tank and then coming back out, swinging its end under the exit pipes as it moves around and over to the end of the lower room, in the area normally occupied by the end bell of the vacuum tank. The tank bell was stowed over against the SE wall, where the south-telescope beam normally enters. 3.) To support the inner end of the granite as it is introduced into the tank, we suspended an I-beam inside the tank by two 1/2-inch threaded rods, extending through holes (normally plugged) that fortuitously exist in the top of the tank. The I-beam was about 12' long, 3" wide, and 6" deep, and accommodated a trolley to which we could attach a heavy nylon sling from the granite. This hardware was preserved from the original installation. 4.) We lifted the crate (cover back in place) with two nylon slings, one under each end, leading up to the tip of the right-hand fork of a big (6'-tine) forklift. The crate hangs parallel to the fork, with the slings held apart by the cleats on the bottom of the crate. The forklift brought the crate as far into the building vestibule as possible, poking the forks right inside the door. We then lowered the crate, such that the inner end came down on a dolly at the bottom of the stairs, and the outer end on the stairs. We then backed the lift out and picked up just the outer end with a single sling and advanced in so as to set the outer end onto a dolly as well. 5.) We rolled the crate through and around, down to the step in the building floor. Note that the dollies must be low enough to get under the corner of the optical table. With the forward end of the crate overhanging the step, we picked up the lower end with a standard auto-garage four-caster hydraulic jack, advanced on the jack casters, and set the end down again on a dolly. Moving the jack to the other end, we lifted that, advanced, and set down again on a dolly. Then we rolled the crate over near the open end of the vacuum tank. 6.) Because the crate is too long to put in line with the tank, we lifted the granite beam out and set it on two rolling platforms so as to maneuver it into position. The lift was by the 2-ton boom crane that we bought for the purpose, using a good aluminum spreader rig, 48" long, that FLWO had obtained on surplus. One rolling platform, that supported the outer end for the whole trip into the tank, was made up of two 2-wheel jacking trucks borrowed from the MMT and lashed together. The other end was a 4-wheel dolly. The maneuvering into place was done with the granite beam supported near floor level. With the beam aligned with the tank, we lifted it again with the crane, built the outer-end device up to the appropriate height, and supported the inner end from the previously installed trolley-I-beam arrangement. 7.) The granite beam now could be rolled smoothly into place, and lowered by controlling the nuts that supported the threaded rod at the top of the tank, on the outside. The inner-end support plate must be carefully leveled in the transverse direction, since it determines the leveling of the granite. With the granite now in place, we could remove the sling, the trolley, and the outer rolling support, and then lower the I-beam on down to rest on wooden blocks on top of the granite. We could then extend the crane boom to its maximum position and reach in to pick up the I-beam near its center of gravity and thus back it out, rolling the crane along. The crane will not roll freely with a load as heavy as the granite, but behaves well with a lighter load. 8.) The final step was to lift the end platform that is cantilevered from the granite, using the crane and nylon slings, and get it bolted back on. The platform had been stored inside the end bell of the vacuum tank. To remove the granite beam again from the tank (hopefully, not until the final de-commissioning of IOTA) all the steps listed above in items 8.) back through 2.) can be done in exact reverse order. When we did it this last time, we did not have the I-beam and trolley organized, and hence just reached in with the crane to support the inner end of the granite (just barely inside the c.g.) and pulled the beam out with a come-along an inch or two at a time, setting down on wooden blocks after each pull and resetting the lifting sling. For the first pulls, with the crane not able to bear nearly the full weight while near the c.g. and with the boom extended, we took only a partial load and slid the inner end along on the inner support plate. This all could be done again, but reversing the re-introduction process looks like the preferred method, although it has not been explicitly tested. Since the top surface of the granite beam had to be stripped for re-finishing on this trip, the carriages were removed before moving the beam, and all the motor-track hardware was removed as soon as the beam was in its crate. Lacking the need to strip, even the carriages could be left in place, I believe, during removal and crating.